Work in Progress

Some projects/roadworks may take a bit longer than anticipated to complete due to extended periods of rain, or contractors being unavailable. Current capital improvement projects are listed here. Other minor capital projects may also be underway.

Choose the suburb or area to see all work being undertaken in that area:

Shire Wide

Pathway Upgrades in Tewantin, Noosaville, Cooran and Cooroy

Project Summary: Council will soon deliver a series of pedestrian infrastructure upgrades across Tewantin, Noosaville, Cooran and Cooroy over the next three months. These works will strengthen connectivity, improve accessibility and support safer walking and cycling routes in line with Council’s Cycling and Walking Strategy, with new and upgraded pathways creating safer, more accessible links for residents and visitors. 

January 2026

  • Diamond Street Pathway, Cooroy –approx. 3 weeks
  • Yellowood Drive & McKinnon Drive, Tewantin – approx. 2 weeks
  • Noosa Parade Pathway, Noosaville– approx. 3 weeks

February 2026

  • Waratah Close Pathway, Tewantin –approx. 3 weeks
  • Werin Street & Shields Street Staircase and Pathway, Tewantin –approx. 4 weeks

March 2026

  • Bridge Street Pathway, Cooran – approx. 4 weeks 

Timeframes are subject to weather conditions.

See Project News(PDF, 903KB) for further information.

 

 

Black Mountain

There are no capital projects scheduled at this time.

Boreen Point

There are no capital projects scheduled at this time.

Castaways Beach

There is currently no capital projects in this area.

Cooran

There are no capital projects scheduled at this time.

 

Cooroibah

There are no capital projects at this time.

Cooroy

Location: Nandroya Road, Cooroy 

Following the storm event on 29 March 2025, instability was identified at the edge of Nandroya Road. Interim stability works have been completed to keep two lanes open to traffic. The lane widths through this section are narrow and motorists are advised to drive to conditions. Investigations into long-term repair options are continuing.

Related document: Works Notice(PDF, 561KB)

Cooroy Mountain

There are no capital projects underway at this time.

Cootharaba

There are no capital projects scheduled at this time.

Doonan

There are no Capital Projects scheduled at this time.

 

Federal

There are no capital projects underway at this time.

Kin Kin

There are no capital projects underway at this time.

Lake Macdonald

Location: Hayward Road - Asphalt Heavy Patching Night Works 

Updated 09/03: Due to wet weather resulting in unsuitable ground conditions, these works have been delayed until further notice.   

Contractors will soon commence asphalt heavy patching works on Hayward Road.

Work is scheduled to commence on 26th February 2026 with completion expected by the same night, subject to weather, contractor availability and site conditions.

Related document: Works Notice(PDF, 99KB)


Location: Lake Macdonald Drive Works

Project: Council contractors are carrying out remediation, and civil works for the subdivision located at 62 & 64 Lake Macdonald Drive, Cooroy to support future uses, including community housing.

Duration: Remediation works are estimated to start in August 2025 and finish in October 2025Subdivision works are estimated to start in October 2025 and finish in January/February 2026.

For further information visit our dedicated page here.

 

Marcus Beach

There are no capital projects underway at this time.

Noosa Heads

Location: Noosa Parade / Lions Park - Drainage Works 

Contractors will soon commence Drainage works on Noosa Parade.

Work is scheduled to commence on Tuesday, 3rd February 2026 with completion expected by Friday, 22nd March 2026, subject to weather, contractor availability and site conditions. The work will be undertaken during the day between the hours of 6.30am and 6.30pm.

Related documents: Works Notice(PDF, 213KB) 


Location: Noosa Sound - Canal and Foreshore Maintenance Dredging

Project: Noosa Council advises that essential foreshore maintenance dredging works will soon recommence within the Noosa Sound canal system. These works aim to maintain safe and navigable waterways and support ongoing foreshore stability.

Project Start Date: Monday, 14 July 2025, Works recommencing 12 January 2026

Estimated Duration: Approximately 6 months  

Construction will take place between 6:30am and 6:30pm, Monday to Saturday. Any updates to the schedule will be published on Council’s website as needed

Note: The schedule is subject to change based on weather conditions, contractor availability, and site circumstances. 


 

 

Noosa North Shore

There are no capital projects scheduled at this time.

 

Noosaville

Location: Eenie Creek Road - Drainage and Landscaping Works

Contractors will soon commence Drainage works on Eenie Creek Rd.

Work is scheduled to commence on Tuesday, 24th March 2026 with completion expected by Thursday, 26th March 2026, subject to weather, contractor availability and site conditions. The work will be undertaken during the day between 5.00am and 6.30pm. 

Every effort will be made to minimise disruptions; however, a lane closure adjacent to the road island will be required in both directions. Traffic will remain open in the left lane, with vehicles funnelled through the work area under traffic control. 

Related documents: Works Notice(PDF, 185KB)


Location: Armitage Court - Pathway Repair Works

Updated 16/02: Due to wet weather resulting in unsuitable ground conditions, these works have been delayed until further notice.   

Contractors will soon concrete pathway work on Armitage Court.

Work is scheduled to commence on Monday, 16th February with completion expected by 20th February 2026, subject to weather, contractor availability and site conditions.

Related documents: Works Notice(PDF, 180KB)


Location: Weyba Road and Mary Street Roundabout - Asphalt Relay Night Works  

Updated 09/03: Due to wet weather resulting in unsuitable ground conditions, these works have been delayed until further notice.   

Contractors will soon commence asphalt relay works on Weyba Road and Mary Street Roundabout.

Work is scheduled to commence on 8th March with completion expected by 11th March 2026 subject to weather, contractor availability and site conditions.

Every effort will be made to minimise the impact, on traffic and the public, however a periodic closure of the area will be necessary to complete the works. Traffic management measures and detours will be in place throughout the works.

Related documents: Works Notice(PDF, 199KB)


Location: Pirate Park - Shade Sail Replacement 

The Pirate Park shade sail was removed after sustaining irreparable damage during the November storm event. A replacement sail has been ordered and is currently in production. Due to manufacturing lead times, installation is anticipated for 19th March 2026, subject to weather conditions, contractor availability, and site requirements.
 
We apologise for any impact on use of the play equipment, and the inconvenience caused.
 
 Related documents: Works Notice(PDF, 148KB)

Location: Quota Park, Gympie Terrace, Noosaville

Project: Build an accredited Public Amenities facility to provide safe, dignified, all-inclusive bathroom amenities for people with high support needs and their carers. 

Concept design: In progress
Final design: due early 2026
Construction phase: mid 2026

Related document: Project News(PDF, 754KB)

Peregian Beach

There are currently no capital works projects in this area.

Pinbarren

There are no capital projects scheduled at this time.

Pomona

Location: Bellbird Flat Rd  and Hawk Road - Asphalt Patching Works

Updated 09/03: Due to wet weather resulting in unsuitable ground conditions, these works have been delayed until further notice.   

Contractors will soon commence asphalt patching works on Bellbird Flat Road and Hawk Road.

Work is scheduled to commence on Monday, 16th March 2026 with completion expected the same day, subject to weather, contractor availability and site conditions. The work will be undertaken during the day between the hours of 6.30am and 6.30pm.

Related documents: Works Notice(PDF, 152KB)


Location: Mountain Street - Asphalt Patching Works

Updated 09/03: Due to wet weather resulting in unsuitable ground conditions, these works have been delayed until further notice.   

Contractors will soon commence Asphalt Patching works on Mountain Street, Pomona.

Work is scheduled to commence on Tuesday, 17th March 2026 with completion expected the same day, subject to weather, contractor availability and site conditions. The work will be undertaken during the day between the hours of 6.30am and 6.30pm.

Related documents: Works Notice(PDF, 188KB)


 

 

 

 

Ridgewood

There are no capital projects scheduled at this time.

Sunrise Beach

Location: Tingira Crescent Hang Gliders Area 

Council’s Environmental and Parks Maintenance teams are currently working collaboratively on a broader revitalisation project for this area. The recent placement of crusher dust is an initial preparatory step and forms a small part of the overall works planned.

The full project will include:

  • Installation of new seating and bollards
  • Relaying of turf
  • Improvements to irrigation
  • Measures to stabilise and protect the site in an environmentally sustainable way.

Duration of works: Work is scheduled to commence Monday, 23rd February 2026, with completion expected by 20th March 2026, subject to weather and site conditions.

Related documents: Works Notice(PDF, 97KB)


Location: Sunshine Creek embankment stabilisation 

In March 2026, Noosa Council will be starting reconstruction works to stabilise the Sunshine Creek embankment at Sunrise Beach. These works will be finished by June 2026, weather and construction conditions permitting.

Refer to the Sunshine Creek embankment page for updates.

 

 


Sunshine Beach

Location: Ed Webb Park - GPT Cleaning Works 

Contractors will soon commence Drainage works in Ed Webb Park.

Work is scheduled to commence on Thursday, 12th March 2026 with completion expected by Friday, 13th March 2026, subject to weather, contractor availability and site conditions.

The work will be undertaken during the day between the hours of 6.30am and 6.30pm.

Related documents: Works Notice(PDF, 250KB)


Location: David Low Way - Height and Width Vegetation Clearance Works

Contractors will soon commence height and width clearance along David Low Way roadway.

Work is scheduled to commence on Monday, 9th March 2026 with completion expected by 19th March 2026, subject to weather, contractor availability and site conditions.

One lane will be intermittently closed at specific points along David Low Way to allow the works to be completed safely. Every effort will be made to minimise the impact, on traffic and the public, however delays of up to 10 minutes can be expected. Traffic management measures will be in place throughout the works.

Related documents: Works Notice(PDF, 204KB)


 

 

 


Tewantin

Location: Tewantin Splash Park - Rubber Resurfacing Works

Council will soon commence resurfacing of the rubber surface at the Tewantin Splash Park located next to the Noosa Marina.

Work is scheduled to commence on Thursday, 12th March 2026 with completion expected by Sunday, 5th April 2026, subject to weather and construction conditions. The work will be undertaken during the day between the hours of 6.30am and 6.30pm.

Every effort will be made to minimise the impact, on traffic and the public, however a periodic closure of the area will be necessary to complete the works.

Related documents: Works Notice(PDF, 174KB)


Location: Moorindil Street - N16 Amenities Refurbishment

Council will soon commence refurbishment works at the public amenities on Moorindil Street, Tewantin.

The amenities will be closed from Monday, 16 February 2026 with the refurbishment expected to take approximately four weeks.

Related documents: Works Notice(PDF, 258KB)


Location: Crank Street and Moorindil Street Roundabout - Asphalt Reseal Night Works

Updated 09/03: Due to wet weather resulting in unsuitable ground conditions, these works have been delayed until further notice.   

Contractors will soon commence Asphalt reseal work on Crank Street & Moorindil Street Roundabout.

Work is scheduled to commence on 12th March with completion expected by 16th March 2026, subject to weather, contractor availability and site conditions.

The work will be undertaken at night between the hours of 6.30pm and 6.30am.

Related documents: Works Notice(PDF, 170KB)


Location: Woolumba St and Wandi Street - Kerb and Channel Works

Contractors will soon commence kerb and channel works on Wandi Street and Woolumba Street. Asphalt resurfacing works will follow shortly after however an additional notice will be issued.

Work is scheduled to commence middle of February 2026 with completion expected by early to mid-March 2026, subject to weather, contractor availability and site conditions. The work will be undertaken during the day between the hours of 6.30am and 6.30pm. 

Related documents: Works Notice(PDF, 207KB)


Location: Outlook Drive and connecting streets - Asphalt Reseal Works

Contractors will soon commence asphalt reseal works on Outlook Drive, Birch Court, Wandi Street, Richardson Court and Freeman Court.

Work is scheduled to commence on 18th March with completion expected by 25th March 2026, subject to weather, contractor availability and site conditions. 

The work will be undertaken during the day between the hours of 6.30am and 6.30pm.

Related document: Work Notice(PDF, 191KB)


Location: Doonella Lake Bridge

Upgrade works on Doonella Lake Bridge in Tewantin are set to commence late May/early June 2026, with work expected to finish by late November 2026, subject to weather and construction conditions. These essential works will improve the bridge’s safety, durability, and accessibility for all road users.

Related document: Project News(PDF, 53KB)

 

Tinbeerwah

Location: Wendoma Street - Asphalt Patching Works

Contractors will soon commence Asphalt Patching works on Wendoma Court, Tinbeerwah.

Work is scheduled to commence on Wednesday 18th March 2026 with completion expected the same day, subject to weather, contractor availability and site conditions.

The work will be undertaken during the day between the hours of 6.30am and 6.30pm.

Related documents: Works Notice(PDF, 176KB)


Location: Sunrise Road - Heavy Patching Works

Contractors will soon commence Asphalt Patching works on Sunrise Road, Tinbeerwah

Work is scheduled to commence on Friday, 20th March 2026 with completion expected the same day, subject to weather, contractor availability and site conditions. The work will be undertaken during the day between the hours of 6.30am and 6.30pm.

Related documents: Works Notice(PDF, 193KB)